Use the options in this menu group to perform such tasks as cleanse, publish, accelerate, and export a schedule.
Field | Description |
Cleanse Schedule
|
Click this icon to display the Cleanse Schedule dialog box to cleanse and resolve flaws in your schedule.
|
Accelerate Schedule
|
Click to accelerate the schedule to meet faster completion deadlines or to get a delayed project back on track. When you use this option, an Acceleration tab is added to the Details pane.
|
Schedule Realism Advisor
|
The advisor provides suggestions for calibrating each activity based on a given criteria. Click to display the Schedule Realism Advisor dialog box to select options and run the advisor.
|
Scenario Calibration
|
Use these options to define settings for scenario calibration:
- Create Scenario creates a new scenario for calibration.
- Run CPM Analysis runs the CPM analysis manually.
- Run CPM Automatically runs the CPM Automatically.
- Calibration Template displays the Calibration Template Editor dialog box which allows you to define the calibration template.
- Unlock All Children unlocks all children of the selected parent. Each time you set a node, it, and its children, become locked so that any subsequent manipulation of uncertainty values higher up in the schedule hierarchy does not impact the explicit change that you made at the node level. Use this option to unlock the children so that you can change their values
|
Export Scenario
|
Click to export (publish) the selected scenario back to its original format (MS Project or Primavera). The file is scheduled/CPM-time analyzed in Acumen before being published and therefore has updated early/late dates, float, and so on.
|
Related Topics